The status of the works on site, as at the date of our site inspection on 10 November 2015, can be briefly described as follows: * Bulk excavation is complete. * Detailed excavation well underway with footings and columns advanced. * Lift pit base and lower basement walls to lift complete. * Form work shutters […]
READ MOREZephyr at Lutwyche is well under way
Zephyr at Lutwyche Update – 31 Oct 2015 Construction is well under way with the basement dug to its final depth and foundations being poured.
READ MOREAspect at Everton Park complete and looking fantastic
Everton Park nearing completion
Everton Park The current status of the works on site, as at the date of our inspection 31 July 2014, can briefly described as follows: * All 33 townhouse structures are complete including cladding, glazing and roofing. * Tiling and plastering complete. * Joinery installation complete. Appliance fitoff underway. * Painting complete to 23 townhouses. […]
READ MOREScaffolding starting to come down at Everton Park
Everton Park on 2 July 2014 The current status of the works on site, as at the date of our inspection 02 July 2014, can briefly described as follows: * All 33 townhouse structures are complete including cladding, glazing and roofing. * Scaffold drop underway. * Plastering complete. * External rendering almost complete. * Electrical, […]
READ MOREEverton Park really starting to take shape
Everton Park – 03 June 2014 The current status of the works on site, as at the date of our inspection 03 June 2014, can briefly described as follows: * All 33 Townhouse with frame, trusses and roofing complete. * Glazing complete to 29 Townhouses. * Rough in of electrical, mechanical and plumbing complete to […]
READ MORESlabs & Framing moving ahead
Everton Park – 4 March 2014 The current status of the works is briefly described as follows: * 17 Townhouse concrete slabs poured. * Framing underway to 5 Townhouses. * Underslab plumbing completed to 33 Townhouse sites. * Civil stormwater and sewer works run through site. Risers installed to all townhouse sites for roof stormwater. […]
READ MOREDevelopment Application Lodged
Lutwyche Zephyr – Thursday 27 February 2014Development Application lodged with a total of 31 x 2 bed units. 20 x 2bed 2 bath 1 car and 11 x 2 bed 1 bath 1 car.
READ MORESlabs going down and Frames going Up
Everton Park – 26 February 2014 Majority of slabs should be down by end of next week. Framing has begun at the Ballinderry Street end of the site. Looking good
READ MORESOLD OUT ALSO – VIRTUE at CLAYFIELD
CLAYFIELD – 14 February 2014 Virtue at Clayfield is now sold out. This 2bed 2bath 1 car product had exceptional finishes, with 2 large bedrooms, North facing living spaces with great light, great storage and lock up garage and private courtyards with own garden. We received a great response from 1st home buyers, owner occupiers […]
READ MORE