In : News Comments : 0 Author : jedda Date : 09 Jul 2018

The status of the works on site, as at the date of my inspection on 9 July 2018 is:

  • The replacement building Contractor, Geocal Constructions, have taken possession of the site;
  • Blockwork walls are complete;
  • Timber wall framing to ground floor and first floor is 90% complete;
  • Concrete slabs, with the exception of a portion to the driveway slab and the courtyard of home 1, are complete;
  • Aluminium windows and doors for the ground floor have been delivered to site for installation; and
  • Electrical and plumbing under-slab services have been installed.
In : News Comments : 0 Author : jedda Date : 04 Jul 2018

Demolition has started on site at Helen Street with the team at Hutchies starting to clear out the internals of the existing building. With the inside almost completely cleared, the building will be set for demolition in the coming weeks. 

In : News Comments : 0 Author : jedda Date : 24 Jun 2018

The status of the works on site, as at the date of our site inspection on 13 June 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
· The overland flow suspended slab was complete.
· The concrete driveway was nearing completion with only one section over a drain remaining.
· Electrical & Plumbing in slab and mains pipework and conduits were complete.
· Blockwork walls were complete to the underside of level 2.
· Framing was complete on both levels to all except 2 units.

In : News Comments : 0 Author : jedda Date : 16 May 2018

The status of the works on site, as at the date of our site inspection on 11 May 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
rear.
· The overland flow suspended slab was complete.
· The concrete cover over the water tank was complete.
· Electrical & Plumbing in slab and mains pipework and conduits were complete.
· Blockwork walls were complete to the underside of level 1.
· Framing was complete to the ground level and 5 of 6 timber floors were complete to Level 1 including floor sheeting
fixed.

In : News Comments : 0 Author : jedda Date : 02 May 2018

The status of the works on site, on 26 April 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
· The overland flow suspended slab was complete.
· The concrete cover over the water tank was complete.
· Electrical & Plumbing in slab and mains pipework and conduits were complete.
· Blockwork walls were complete to the underside of level 1.
· Framing was complete to the ground level and 2 of 6 timber floors were complete to Level 1 including floor sheeting fixed, 2 additional 2 Level 1 mid floors had joists installed.

In : News Comments : 0 Author : jedda Date : 13 Apr 2018

The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows:

· Site had been fully established including office and amenities.

· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.

· The overland flow suspended slab was nearing completion with the driveway section ready to be poured.

· Electrical & Plumbing in slab services were complete.

· Blockwork walls were complete to the underside of level 1.

· Framing was complete to the ground level was complete.

· Blockwork for the retention basin is complete and waterproofed.

· Major Stormwater drainage civil works were essentially complete.

In : News Comments : 0 Author : jedda Date : 04 Apr 2018

The status of the works on site, as at the date of our site inspection on 26 March 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
rear.
· The suspended slab was complete with the exception of the driveway portion.
· Electrical & Plumbing in slab services were complete.
· Blockwork walls were complete to the underside of level 1.
· Framing was complete to the ground level in 2 of 6 townhouses.
· Blockwork for the retention basin is complete and waterproofed.
· Major Stormwater drainage civil works were essentially complete.

In : News Comments : 0 Author : jedda Date : 26 Mar 2018

The status of the works on site, as at the date of our site inspection on 09 March 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
rear.
· The suspended slab was complete with the exception of the driveway portion.
· Electrical & Plumbing in slab services were complete.
· Blockwork for the retention basin is complete and waterproofed.
· Major Stormwater drainage civil works were essentially complete.

In : News, Sin categoría Comments : 0 Author : jedda Date : 27 Feb 2018

The status of the works on site, as at the date of our site inspection on 27 February 2018, can be briefly described as
follows:
· Site had been fully established including office and amenities.
· Bulk excavation works were complete.
· Detailed excavation was complete.
· Footings and blockwork retaining walls were complete except to the front of the site.
· The columns to support the underside of the overland flow and suspended slab were complete.
· The Propping, formwork and reinforcing for the suspended slab were complete ready for pouring.
· Blockwork for the retention basin is complete and waterproofed.
· Major Stormwater drainage civil works were essentially complete.

In : News, Sin categoría Comments : 0 Author : jedda Date : 26 Jan 2018

Canopy at Taringa is beginning to take shape. The site is fully established with onsite office and amenities. Shake down crossover established with a bulk and detailed excavation works well advanced and onsite stock pile left to back fill. Footings and blockwork retaining walls are well advanced to the back and sides of the site, with pier holes dug and concrete poured for footings in regards to suspended slab. Major Stormwater draining civil works are well advanced on site as well.