In : News Comments : 0 Author : jedda Date : 02 Oct 2018

The status of works on site as of the 25th of September:

  • Blockwork retaining walls were complete except to the front of the site and a minor section at the rear
  • The overland flow suspended slab was complete and the remainder of the driveway is being poured 
  • Framing was complete and plasterboard sheeting was complete to 5 of 6 units upstairs and 4 of 6 units downstairs 
  • Stairs installed to all units 
  • Roof is nearing completion with installation of soffits and down pipes remaining
  • The external cladding was complete with only minor single boards remaining for installation 
  • Glazing has well advanced with only some front doors and sliding doors remaining to be installed. 
  • Electrical rough in's completed throughout 
  • Mechanical Head units installed and ducting complete with only the condenser units remaining 
  • Render to the blockwork walls mostly complete and privacy fencing posts installed
In : News, Sin categoría Comments : 0 Author : jedda Date : 13 Sep 2018

The status of works as of the 13th of September:

  • Stairs to begin this Friday 
  • All plumbing rough in tested and passed internally 
  • Wiring rough in and AC completed 
  • Sheeting internal should be completed by end of next week (3 units upstairs completed at present, setting to start by end of the week)
  • Tiles have arrived on site, as soon as stairs are completed upstairs internal walls will be tiled
  • Unit 6 structural steel is onsite and should be installed by end of the week 
  • Front area works to start on Monday 
  • Joinery contractor will check measurements tomorrow and start production 
In : News, Sin categoría Comments : 0 Author : jedda Date : 22 Aug 2018

The status of works as of the 22nd of August:

  • Scaffolding around the site has come down 
  • Roof is nearing completion with installation of soffits and flashing remaining
  • External cladding advanced with one side remaining for installation 
  • External painting has begun 
  • Framing completed on both levels and rough in services underway and sheeting has commenced on Ground Level
  • Windows and door installation 90% complete 
  • Plumbing and electrical in slab and mains pipework and conduits completed 
  • Glazing was advanced
  • Communication with cabinet contracts underway
In : News Comments : 0 Author : jedda Date : 21 Aug 2018

Demolition of the building on site at Helen Street for Obsidian has commenced over the last week. Earlier during the week saw demolition contractors prepping the site with propping of walls and preparation of trusses. On Saturday demolition started with the removal of both side walls and partial removal of the back wall. 

In : News Comments : 0 Author : jedda Date : 08 Aug 2018

The status of works as of the 8th of August:

  • Roof trussing and sheeting completed last week 
  • Ground level glazing has commenced, as well as rough plumbing and electrical services
  • Level 1 glazing to 90% of the project as well as rough electrical services 
  • Exterior cladding and painting to level 1 
  • Installation of insulation
In : News, Sin categoría Comments : 0 Author : jedda Date : 20 Jul 2018

The status of the works on site as of the 18th of July 2018:

  • Geocal have fully secured the site with fencing and scaffolding to the entire site setup 
  • Geocal contractors on site for framing , roofing and window installation 
  • Framing completed 100% for both ground and level one 
  • Roof trusses 90% complete 
  • Window installation to 40% of ground level 
 
In : News Comments : 0 Author : jedda Date : 09 Jul 2018

The status of the works on site, as at the date of my inspection on 9 July 2018 is:

  • The replacement building Contractor, Geocal Constructions, have taken possession of the site;
  • Blockwork walls are complete;
  • Timber wall framing to ground floor and first floor is 90% complete;
  • Concrete slabs, with the exception of a portion to the driveway slab and the courtyard of home 1, are complete;
  • Aluminium windows and doors for the ground floor have been delivered to site for installation; and
  • Electrical and plumbing under-slab services have been installed.
In : News Comments : 0 Author : jedda Date : 04 Jul 2018

Demolition has started on site at Helen Street with the team at Hutchies starting to clear out the internals of the existing building. With the inside almost completely cleared, the building will be set for demolition in the coming weeks. 

In : News Comments : 0 Author : jedda Date : 24 Jun 2018

The status of the works on site, as at the date of our site inspection on 13 June 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
· The overland flow suspended slab was complete.
· The concrete driveway was nearing completion with only one section over a drain remaining.
· Electrical & Plumbing in slab and mains pipework and conduits were complete.
· Blockwork walls were complete to the underside of level 2.
· Framing was complete on both levels to all except 2 units.

In : News Comments : 0 Author : jedda Date : 16 May 2018

The status of the works on site, as at the date of our site inspection on 11 May 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
rear.
· The overland flow suspended slab was complete.
· The concrete cover over the water tank was complete.
· Electrical & Plumbing in slab and mains pipework and conduits were complete.
· Blockwork walls were complete to the underside of level 1.
· Framing was complete to the ground level and 5 of 6 timber floors were complete to Level 1 including floor sheeting
fixed.