Canopy at Taringa is beginning to take shape. The site is fully established with onsite office and amenities. Shake down crossover established with a bulk and detailed excavation works well advanced and onsite stock pile left to back fill. Footings and blockwork retaining walls are well advanced to the back and sides of the site, with pier holes dug and concrete poured for footings in regards to suspended slab. Major Stormwater draining civil works are well advanced on site as well.