Everton Park
The current status of the works on site, as at the date of our inspection 31 July 2014, can briefly described as follows:
* All 33 townhouse structures are complete including cladding, glazing and roofing.
* Tiling and plastering complete.
* Joinery installation complete. Appliance fitoff underway.
* Painting complete to 23 townhouses.
* Electrical fit off complete to 20 townhouses.
* Plumbing fitoff complete to 21 townhouses.
* Mechanical fit off complete to 26 townhouses.
* Patio and paths poured.
* Driveway works underway.