The status of the works on site as of the 18th of July 2018:
- Geocal have fully secured the site with fencing and scaffolding to the entire site setupÂ
- Geocal contractors on site for framing , roofing and window installationÂ
- Framing completed 100% for both ground and level oneÂ
- Roof trusses 90% completeÂ
- Window installation to 40% of ground levelÂ