The status of the works on site as of the 18th of July 2018:
- Geocal have fully secured the site with fencing and scaffolding to the entire site setup
- Geocal contractors on site for framing , roofing and window installation
- Framing completed 100% for both ground and level one
- Roof trusses 90% complete
- Window installation to 40% of ground level
Sorry, the comment form is closed at this time.