Everton Park – 4 March 2014
The current status of the works is briefly described as follows:
* 17 Townhouse concrete slabs poured.
* Framing underway to 5 Townhouses.
* Underslab plumbing completed to 33 Townhouse sites.
* Civil stormwater and sewer works run through site. Risers installed to all townhouse sites for roof stormwater.
* Detailed excavation completed, backfilling around rear of slab sites completed.
* Main Switchboard in place