The status of the works on site, as at the date of our site inspection on 26 March 2018, can be briefly described as follows:
- Site had been fully established including office and amenities.
- ยท Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
- The suspended slab was complete with the exception of the driveway portion.
- Electrical & Plumbing in slab services were complete.
- Blockwork walls were complete to the underside of level 1.
- Framing was complete to the ground level in 2 of 6 townhouses.
- Blockwork for the retention basin is complete and waterproofed.
- Major Stormwater drainage civil works were essentially complete.