Canopy Taringa – April Update

The status of the works on site, as at the date of our site inspection on 26 March 2018, can be briefly described as follows:

  • Site had been fully established including office and amenities.
  • ยท Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
  • The suspended slab was complete with the exception of the driveway portion.
  • Electrical & Plumbing in slab services were complete.
  • Blockwork walls were complete to the underside of level 1.
  • Framing was complete to the ground level in 2 of 6 townhouses.
  • Blockwork for the retention basin is complete and waterproofed.
  • Major Stormwater drainage civil works were essentially complete.