The status of the works on site, as at the date of inspection on 03 February 2016:
- Bulk and detailed excavation is complete.
- Bio-retention tank and pump in.
- Basement slabs complete.
- Vehicular ramp and Level 1 [1st pour] underway at the time of inspection.
- Remainder of Level 1 Form work is in place.
- Steel reinforcement in place for Level 1 -1st pour.
- Waterproofing complete to external of basement block walls and back filling commenced.