We are out of the ground

The status of the works on site, as at the date of inspection on 03 February 2016:

  • Bulk and detailed excavation is complete.
  • Bio-retention tank and pump in.
  • Basement slabs complete.
  • Vehicular ramp and Level 1 [1st pour] underway at the time of inspection.
  • Remainder of Level 1 Form work is in place.
  • Steel reinforcement in place for Level 1 -1st pour.
  • Waterproofing complete to external of basement block walls and back filling commenced.