Canopy at Taringa is well underway with the team at Truform having fully established the site with onsite office and amenities. Bulk excavation works of the site have well advanced with onsite stock pile left to back fill. Detailed excavation has well advanced along with footings and blockwork retaining walls to the back and sides of the site. Pier holes are dug and concrete poured for footings in regards to suspended slab and major stormwater drainage civil works were advancing well.
The team at Truform are well on schedule to bringing these 3 bedroom designers homes to life.
Sorry, the comment form is closed at this time.