Canopy Taringa – mid April Update

The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows:

  • Site had been fully established including office and amenities.
  • Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
  • The overland flow suspended slab was nearing completion with the driveway section ready to be poured.
  • Electrical & Plumbing in slab services were complete.
  • Blockwork walls were complete to the underside of level 1.
  • Framing was complete to the ground level was complete.
  • Blockwork for the retention basin is complete and waterproofed.
  • Major Stormwater drainage civil works were essentially complete.