The status of works as of the 13th of September:

  • Stairs to begin this Friday 
  • All plumbing rough in tested and passed internally 
  • Wiring rough in and AC completed 
  • Sheeting internal should be completed by end of next week (3 units upstairs completed at present, setting to start by end of the week)
  • Tiles have arrived on site, as soon as stairs are completed upstairs internal walls will be tiled
  • Unit 6 structural steel is onsite and should be installed by end of the week 
  • Front area works to start on Monday 
  • Joinery contractor will check measurements tomorrow and start production 