13 Sep Canopy – September Update
The status of works as of the 13th of September:
- Stairs to begin this FridayÂ
- All plumbing rough in tested and passed internallyÂ
- Wiring rough in and AC completedÂ
- Sheeting internal should be completed by end of next week (3 units upstairs completed at present, setting to start by end of the week)
- Tiles have arrived on site, as soon as stairs are completed upstairs internal walls will be tiled
- Unit 6 structural steel is onsite and should be installed by end of the weekÂ
- Front area works to start on MondayÂ
- Joinery contractor will check measurements tomorrow and start productionÂ