Menu
Canopy – Late September Update

Canopy – Late September Update

The status of works on site as of the 25th of September:

  • Blockwork retaining walls were complete except to the front of the site and a minor section at the rear
  • The overland flow suspended slab was complete and the remainder of the driveway is being poured
  • Framing was complete and plasterboard sheeting was complete to 5 of 6 units upstairs and 4 of 6 units downstairs
  • Stairs installed to all units
  • Roof is nearing completion with installation of soffits and down pipes remaining
  • The external cladding was complete with only minor single boards remaining for installation
  • Glazing has well advanced with only some front doors and sliding doors remaining to be installed.
  • Electrical rough in’s completed throughout
  • Mechanical Head units installed and ducting complete with only the condenser units remaining
  • Render to the blockwork walls mostly complete and privacy fencing posts installed
No Comments

Sorry, the comment form is closed at this time.