In : Aspect Everton Park, News Comments : 0 Author : agent49 Date : 24 May 2017

After 2-3 years Visie Development Projects still look pretty amazing.   All Visie developments projects are meticulous in design and landscaping, that’s why they look so good even after the project has long been completed.

These are actual photographs of the project.  You can see the beautiful landscape set against the afternoon backdrop.  This is typical of all Visie Development Projects, we build to encompass the surrounding environment.    Visie Properties not only creates architecturally stunning building designs, they also make sure that landscaping lasts for many years beyond project completion.

Another job well done from the team at Visie Properties.

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 02 Dec 2014
In : Aspect Everton Park, News Comments : 0 Author : Media Date : 21 Aug 2014

Everton Park

 

The current status of the works on site, as at the date of our inspection 31 July 2014, can briefly described as follows:

* All 33 townhouse structures are complete including cladding, glazing and roofing.

* Tiling and plastering complete.

* Joinery installation complete. Appliance fitoff underway.

* Painting complete to 23 townhouses.

* Electrical fit off complete to 20 townhouses.

* Plumbing fitoff complete to 21 townhouses.

* Mechanical fit off complete to 26 townhouses.

* Patio and paths poured.

* Driveway works underway.

 

 

 

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 03 Jul 2014

Everton Park on 2 July 2014

 

The current status of the works on site, as at the date of our inspection 02 July 2014, can briefly described as follows:

 

* All 33 townhouse structures are complete including cladding, glazing and roofing.

* Scaffold drop underway.

* Plastering complete.

* External rendering almost complete.

* Electrical, plumbing and mechanical fit off is underway.

* Roller door installation underway.

* Tiling well underway,

* Internal painting well underway.

* Joinery installation underway including bench tops and vanities.

 

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 19 Jun 2014

Everton Park - 03 June 2014

The current status of the works on site, as at the date of our inspection 03 June 2014, can briefly described as follows:

* All 33 Townhouse with frame, trusses and roofing complete.

* Glazing complete to 29 Townhouses.

* Rough in of electrical, mechanical and plumbing complete to all Townhouses.

* External cladding complete to 14 Townhouses, underway to a further 7 Townhouses.

* Plastering complete to 16 Townhouses, underway to a further 9 Townhouses.

* Joinery including kitchens and vanities installed to 8 Townhouses.

* External painting well underway, internal painting has commenced.

 

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 07 Mar 2014

Everton Park - 4 March 2014

 

The current status of the works is briefly described as follows:

* 17 Townhouse concrete slabs poured.

* Framing underway to 5 Townhouses.

* Underslab plumbing completed to 33 Townhouse sites.

* Civil stormwater and sewer works run through site. Risers installed to all townhouse sites for roof stormwater.

* Detailed excavation completed, backfilling around rear of slab sites completed.

* Main Switchboard in place

 

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 04 Mar 2014

Everton Park - 26 February 2014

Majority of slabs should be down by end of next week.  Framing has begun at the Ballinderry Street end of the site. Looking good

 

 

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 14 Feb 2014

EVERTON PARK – 14 February 2014

Aspect at Everton Park is completely sold out, and only 2 months into commencement of construction.  Aspects town homes proved very popular with 3 bed 2.5bath 2 car at an affordable price point and in a fantastic location.

 

sold out

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 14 Feb 2014

EVERTON PARK 12 February 2014

* Bulk excavation completed, detailed excavation well underway.
* External fencing completed.
* Blockwork retainer walls well advanced.
* Civil stormwater and sewer works well underway through site.
* Townhouse underslab plumbing complete.

In : Aspect Everton Park, News Comments : 0 Author : Media Date : 13 Dec 2013

EVERTON PARK

Civil works well under way, retaining walls in, pads cut, front detention tank in, great outlooks, nice breezes in the afternoon, looking good.