Framework To Level 2 Is Almost Complete Featured

Framework to Level 2 is almost complete

Zephyr Update April 2016

Framework To Level 2 Is Almost Complete Featured

Update April 2016

* Basement mechanical ventilation installation is underway.

* Basement storage compartment framing and sheeting is complete.

* Ground floor slabs are complete.

* Level 1 [transfer] slab is complete.

* Block work from Level 1 to Level 2 is basically complete.

* Formwork to Level 2 slab is at 60%.

* Ground floor units stripped out and internal steel wall framing is well underway.

* Electrical rough in has commenced to Ground Floor units.

* Lift shaft and stairwell walls complete above Level 2