Zephyr Update April 2016
Update April 2016
* Basement mechanical ventilation installation is underway.
* Basement storage compartment framing and sheeting is complete.
* Ground floor slabs are complete.
* Level 1 [transfer] slab is complete.
* Block work from Level 1 to Level 2 is basically complete.
* Formwork to Level 2 slab is at 60%.
* Ground floor units stripped out and internal steel wall framing is well underway.
* Electrical rough in has commenced to Ground Floor units.
* Lift shaft and stairwell walls complete above Level 2