Crane is in and 1st floor on its way

The status of the works on site, as at the date of our site inspection on 03 March 2016:

* Basement slab is complete and temporary services including lighting installed.

* Vehicular ramp is poured and complete.

* Block work and columns complete up to under side of Level 2.

* Level 2 Form work at 50%.

* Lift shaft and stairwell walls complete to underside of Level 2.