The current status of the works on site, as at the date of our inspection 03 June 2014, can briefly described as follows:
* All 33 Townhouse with frame, trusses and roofing complete.
* Glazing complete to 29 Townhouses.
* Rough in of electrical, mechanical and plumbing complete to all Townhouses.
* External cladding complete to 14 Townhouses, underway to a further 7 Townhouses.
* Plastering complete to 16 Townhouses, underway to a further 9 Townhouses.
* Joinery including kitchens and vanities installed to 8 Townhouses.
* External painting well underway, internal painting has commenced.