Canopy Mid August Update

The status of works as of the 22nd of August:

  • Scaffolding around the site has come down 
  • Roof is nearing completion with installation of soffits and flashing remaining
  • External cladding advanced with one side remaining for installation 
  • External painting has begun 
  • Framing completed on both levels and rough in services underway and sheeting has commenced on Ground Level
  • Windows and door installation 90% complete 
  • Plumbing and electrical in slab and mains pipework and conduits completed 
  • Glazing was advanced
  • Communication with cabinet contracts underway