Canopy Taringa November Update Featured

Canopy Taringa – Mid May Update

The status of the works on site, as at the date of our site inspection on 11 May 2018, can be briefly described as follows:

  • Site had been fully established including office and amenities.
  • Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
    rear.
  • The overland flow suspended slab was complete.
  • The concrete cover over the water tank was complete.
  • Electrical & Plumbing in slab and mains pipework and conduits were complete.
  • Blockwork walls were complete to the underside of level 1.
  • Framing was complete to the ground level and 5 of 6 timber floors were complete to Level 1 including floor sheeting
    fixed.