The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows:
- Site had been fully established including office and amenities.
- Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
- The overland flow suspended slab was nearing completion with the driveway section ready to be poured.
- Electrical & Plumbing in slab services were complete.
- Blockwork walls were complete to the underside of level 1.
- Framing was complete to the ground level was complete.
- Blockwork for the retention basin is complete and waterproofed.
- Major Stormwater drainage civil works were essentially complete.