Update June 2016
The status of the works on site, as at the date of our site inspection on 07 June 2016, can be briefly described as follows;
* Basement mechanical ventilation installation continues.
* Basement fit off of electrical and fire well advanced. Plumbing under slung complete.
* Concrete slabs complete.
* Level 1 glazing, water proofing, internal framing, rough in of electrical, mechanical and plumbing services complete. Plaster sheeting onsite but not yet commenced.
* Level 2 glazing, water proofing, internal framing, rough in of electrical, mechanical and plumbing services complete. Plaster sheeting onsite but not yet commenced.
* Level 3 water proofing, internal framing, rough in of electrical, mechanical and plumbing services complete.
* Level 4 internal framing underway.
* Level 5 Block work almost complete with core filling and final block work from ceiling height on level 5 to underside of roof sheeting complete.
* Roof trussing to commence next week. Roof sheeting to be completed in late June 2016.
* Anticipated crane drop is early July 2016.