Zephyr Lutwyche Update 1

Zephyr Lutwyche – Update

Update June 2016

The status of the works on site, as at the date of our site inspection on 07 June 2016, can be briefly described as follows;

* Basement mechanical ventilation installation continues.

* Basement fit off of electrical and fire well advanced. Plumbing under slung complete.

* Concrete slabs complete.

* Level 1 glazing, water proofing, internal framing, rough in of electrical, mechanical and plumbing services complete. Plaster sheeting onsite but not yet commenced.

* Level 2 glazing, water proofing, internal framing, rough in of electrical, mechanical and plumbing services complete. Plaster sheeting onsite but not yet commenced.

* Level 3 water proofing, internal framing, rough in of electrical, mechanical and plumbing services complete.

* Level 4 internal framing underway.

* Level 5 Block work almost complete with core filling and final block work from ceiling height on level 5 to underside of roof sheeting complete.

* Roof trussing to commence next week. Roof sheeting to be completed in late June 2016.

* Anticipated crane drop is early July 2016.

 