In : News, Sin categoría Comments : 0 Author : jedda Date : 22 Aug 2018

The status of works as of the 22nd of August:

  • Scaffolding around the site has come down 
  • Roof is nearing completion with installation of soffits and flashing remaining
  • External cladding advanced with one side remaining for installation 
  • External painting has begun 
  • Framing completed on both levels and rough in services underway and sheeting has commenced on Ground Level
  • Windows and door installation 90% complete 
  • Plumbing and electrical in slab and mains pipework and conduits completed 
  • Glazing was advanced
  • Communication with cabinet contracts underway
In : News Comments : 0 Author : jedda Date : 21 Aug 2018

Demolition of the building on site at Helen Street for Obsidian has commenced over the last week. Earlier during the week saw demolition contractors prepping the site with propping of walls and preparation of trusses. On Saturday demolition started with the removal of both side walls and partial removal of the back wall. 

In : News Comments : 0 Author : jedda Date : 08 Aug 2018

The status of works as of the 8th of August:

  • Roof trussing and sheeting completed last week 
  • Ground level glazing has commenced, as well as rough plumbing and electrical services
  • Level 1 glazing to 90% of the project as well as rough electrical services 
  • Exterior cladding and painting to level 1 
  • Installation of insulation