The status of the works on site, as at the date of my inspection on 9 July 2018 is:

  • The replacement building Contractor, Geocal Constructions, have taken possession of the site;
  • Blockwork walls are complete;
  • Timber wall framing to ground floor and first floor is 90% complete;
  • Concrete slabs, with the exception of a portion to the driveway slab and the courtyard of home 1, are complete;
  • Aluminium windows and doors for the ground floor have been delivered to site for installation; and
  • Electrical and plumbing under-slab services have been installed.