In : News Comments : 0 Author : jedda Date : 02 May 2018

The status of the works on site, on 26 April 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.
· The overland flow suspended slab was complete.
· The concrete cover over the water tank was complete.
· Electrical & Plumbing in slab and mains pipework and conduits were complete.
· Blockwork walls were complete to the underside of level 1.
· Framing was complete to the ground level and 2 of 6 timber floors were complete to Level 1 including floor sheeting fixed, 2 additional 2 Level 1 mid floors had joists installed.

Canopy Taringa - mid April UpdateCanopy Taringa - Mid May Update