The status of the works on site, as at the date of our site inspection on 11 May 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. […]
READ MOREArchives for May 2018
Canopy Taringa – May Update
The status of the works on site, on 26 April 2018, can be briefly described as follows: Site had been fully established including office and amenities. Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear. The overland flow suspended slab was complete. The […]
READ MORE