The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows:

· Site had been fully established including office and amenities.

· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.

· The overland flow suspended slab was nearing completion with the driveway section ready to be poured.

· Electrical & Plumbing in slab services were complete.

· Blockwork walls were complete to the underside of level 1.

· Framing was complete to the ground level was complete.

· Blockwork for the retention basin is complete and waterproofed.

· Major Stormwater drainage civil works were essentially complete.