In : News Comments : 0 Author : jedda Date : 13 Apr 2018

The status of the works on site, as at the date of our site inspection on 10 April 2018, can be briefly described as follows:

· Site had been fully established including office and amenities.

· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the rear.

· The overland flow suspended slab was nearing completion with the driveway section ready to be poured.

· Electrical & Plumbing in slab services were complete.

· Blockwork walls were complete to the underside of level 1.

· Framing was complete to the ground level was complete.

· Blockwork for the retention basin is complete and waterproofed.

· Major Stormwater drainage civil works were essentially complete.

In : News Comments : 0 Author : jedda Date : 04 Apr 2018

The status of the works on site, as at the date of our site inspection on 26 March 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
rear.
· The suspended slab was complete with the exception of the driveway portion.
· Electrical & Plumbing in slab services were complete.
· Blockwork walls were complete to the underside of level 1.
· Framing was complete to the ground level in 2 of 6 townhouses.
· Blockwork for the retention basin is complete and waterproofed.
· Major Stormwater drainage civil works were essentially complete.