In : News Comments : 0 Author : jedda Date : 26 Mar 2018

The status of the works on site, as at the date of our site inspection on 09 March 2018, can be briefly described as follows:
· Site had been fully established including office and amenities.
· Footings and blockwork retaining walls were complete except to the front of the site and a minor section at the
rear.
· The suspended slab was complete with the exception of the driveway portion.
· Electrical & Plumbing in slab services were complete.
· Blockwork for the retention basin is complete and waterproofed.
· Major Stormwater drainage civil works were essentially complete.