The status of the works on site, as at the date of our site inspection on 27 February 2018, can be briefly described as
follows:
· Site had been fully established including office and amenities.
· Bulk excavation works were complete.
· Detailed excavation was complete.
· Footings and blockwork retaining walls were complete except to the front of the site.
· The columns to support the underside of the overland flow and suspended slab were complete.
· The Propping, formwork and reinforcing for the suspended slab were complete ready for pouring.
· Blockwork for the retention basin is complete and waterproofed.
· Major Stormwater drainage civil works were essentially complete.