In : News, Zephyr, Lutwyche Comments : 0 Author : Media Date : 08 Feb 2016


The status of the works on site, as at the date of inspection on 03 February 2016:

* Bulk and detailed excavation is complete.
* Bio-retention tank and pump in.
* Basement slabs complete.
* Vehicular ramp and Level 1 [1st pour] underway at the time of inspection.
* Remainder of Level 1 Form work is in place.
* Steel reinforcement in place for Level 1 -1st pour.
* Waterproofing complete to external of basement block walls and back filling commenced.