Everton Park – 03 June 2014 The current status of the works on site, as at the date of our inspection 03 June 2014, can briefly described as follows: * All 33 Townhouse with frame, trusses and roofing complete. * Glazing complete to 29 Townhouses. * Rough in of electrical, mechanical and plumbing complete to […]